Project Plan

Time Frame

Project start date: Thursday 21st March (Induction Day)

Project completion date: Wednesday 29th May (End of week 10)

 

Working Days: Monday-Thursday

Working Hours: 9:30am-5pm (with half hour lunch)

= 7 hours per day

= 28 hours per week

= 280 hours to complete the project

 

Video 1 – ‘Meet The Chair’

Approximately take: 4 weeks

(1 week to prepare, 1 week to shoot, and 1 week to edit)

Start date: 08/04/2013

Completion date:  Friday 03/05/2013

 

Video 2 – ‘UKITA Members Profile Tour’

Approximately take: 3 weeks

(1 week to prepare, 1 week to shoot, and 1 week to edit)

Start date: 08/04/2013

Completion date: Friday 26/04/2013

 

Video 3 – ‘Under the UKITA Umbrella’

Approximately take: 7 weeks

(4 weeks to draw animations, one week to shoot frames, two weeks to edit)

Start date: 08/04/2013

Completion date: Friday 24/05/2013

 

Video 4 -‘How to Maximise Your UKITA Membership’

Approximately take: 7 weeks

(2 weeks to prepare, 1 week to shoot, and 4 weeks to edit and add animations)

Start date: 08/04/2013

Completion date: Friday 24/05/2013

 

From Friday 24/05/2013 – Wednesday 29/05/2013, this last few days will be spend completing editing and polishing the videos ready to present to UKITA